NAME OF PROJECT

Conveyor improvement due to cycle time reduction

client-moncobra

CLIENT: FORD WERKE GmbH

period-moncobra

PERIOD OF EXECUTION: July 2016 – October 2016

amount-moncobra

AMOUNT OF THE PROJECT: 150.000 €

NAME-OF-PROJECT-COLOR

DESCRIPTION OF THE WORKS

Implementation of B479 and the new shift pattern (2 shifts instead of 3) it is required to reduce the cycle time of specific conveyor systems. The scope of work contains mainly investigation of the conveyor systems, modification of systems (if possible) or new design of systems, mechanical and electrical modification and installation, programming + commissioning.
• Chassis EMS Switch in Final Line, Wheel Distribution, Chassis EMS Unloading, Chassis EMS Exchange of Crossing Switch, Chassis EMS Switch in Trim Line Investigation, Trim Unloading, POF investigation (71 Seconds).
-Investigation
-New Design
-Engineering + Building
-Delivery, transport
-Electrical and mechanical Installation
-Programming
-Connection to network
-Testing + Commissioning